| Metric | Q2'26 | Q3'26 | Change |
|---|---|---|---|
| Operating EPS | $0.79, incl. 3c 45Z credits | $1.28, incl. 5c 45Z credits + 5c weather | +62% QoQ, but ~8% of the print is non-recurring credits/weather |
| GAAP EPS | $0.37 | $1.30 | GAAP/operating gap nearly closed |
| Data center pipeline (total, various stages) | 53GW | 54GW | +1GW QoQ (+1.9%), slowest sequential add disclosed |
| Data center ESA-contracted capacity | 'approximately 12GW' | 'over 12GW' | No exact figure given either quarter; denominator obscured |
| Cumulative contract adds since YE2025 | +5GW, 11% | +6GW, 13% | Headline framing up, but masks QoQ deceleration |
| LTM weather-normal electric sales growth | Not disclosed as a rate; only 'strong sales' language | 3.4% across DEV/DESC | New quantified disclosure this quarter |
| FFO to debt | Above 15% (FY25 and Q2 LTM) | Not restated this quarter; only general reaffirmation of 'credit... guidance' without a specific ratio | Specific credit metric dropped from materials |
| CVOW % complete | 81% | 85% | +4 pts |
| CVOW turbines installed | 31 | 44 | +13 turbines in the quarter |
| CVOW project budget | $11.65B incl. $123M unused contingency | $11.65B incl. $123M unused contingency | Unchanged, but contingency being drawn on |