| Metric | Q2'25 | Q3'25 | Change |
|---|---|---|---|
| Operating EPS | $0.75 Q2 2025 | $1.06 Q3 2025 | +$0.31 quarter sequential |
| Data Center Contracts Total | 40 GW Dec 2024 | 47 GW Sept 2025 | +7 GW or 17% growth in 9 months |
| Data Center Construction LOAs | 5 GW Dec 2024 | 9 GW Sept 2025 | +73% spike in binding commitments |
| Data Center ESAs | 9 GW Dec 2024 | 10 GW Sept 2025 | +12% growth in contracted service |
| CVOW Project Cost | $10.9B Q2 2025 | $11.2B Q3 2025 | +$300M increase, unused contingency down to $206M |
| CVOW Monopile Progress | 134 installed (76%) | 176 installed (100%) | Completed 1 month ahead of schedule |
| Weather Impact | Tailwind through 6 months | $0.02 headwind through 10 months | Weather reversal from positive to negative |
| Virginia Peak Demand Records | Not disclosed | 9 of top 10 all-time peaks occurred this year | Unprecedented demand acceleration |
| CVOW LCOE | $63/MWh Q2 | $84/MWh Q3 | +$21/MWh driven by lower REC prices |
| PJM Transmission Awards | $3B in last window | Largest proposed investment since open window began | Significant upside potential for 2026 |