| Metric | Q4'25 | Q1'26 | Change |
|---|---|---|---|
| Operating EPS | $3.42 (2025 full year) | $0.95 Q1 | Strong start tracking to $3.50-3.60 2026 guide |
| Data Center Pipeline | 48GW total capacity | 50GW+ total capacity | +2GW modest expansion |
| Data Center ESAs | ~10GW contracted | 10.4GW contracted | +400MW signed contracts |
| CVOW Budget | $11.5B | $11.4B | -$100M cost reduction |
| CVOW Unused Contingency | $155M | $123M | -$32M contingency burn |
| CVOW Turbine Progress | First turbine completed January | 9 turbines completed, 2-day avg on last 4 | Accelerating installation cadence |
| Common Equity Issued YTD | $0 (start of year) | $1.2B via ATM | Heavy equity issuance pace |
| FFO-to-Debt | Above 15% (2025) | Above 15% Q1 LTM | Maintained credit strength |
| Five-Year CapEx Plan | $65B (February guide) | $65B reaffirmed | No change but storage upside noted |
| Virginia Storage Target | 3GW by 2035 | 20GW by 2045 mandated | +567% storage requirement increase |