| Metric | Q1'26 | Q2'26 | Change |
|---|---|---|---|
| Operating EPS | $0.95 (Q1 2026) | $0.79 (Q2 2026) | -17% sequential decline |
| Data Center Pipeline | 50GW (Q1 2026) | 53GW (Q2 2026) | +6% quarter-over-quarter |
| Contracted Data Centers | 10.4GW (Q1 2026) | 12GW (Q2 2026) | +1.6GW new contracts |
| CVOW Completion | 75% (Q1 2026) | 81% (Q2 2026) | +600bps progress |
| CVOW Project Cost | $11.4B (Q1 2026) | $11.65B (Q2 2026) | +$250M or 2.2% increase |
| Turbines Installed | 9 (Q1 2026) | 31 (Q2 2026) | +244% quarter-over-quarter |
| CVOW Unused Contingency | $123M (Q1 2026) | $123M (Q2 2026) | Unchanged despite cost increase |
| FFO to Debt | >15% (Q1 LTM) | >15% (Q2 LTM) | Maintained above target |
| Common Equity Issued YTD | $1.2B (Q1 2026) | Complete for 2026 | ATM program finished early |
| OSHA Recordable Rate | 0.42 (Q1 2026) | 0.36 (Q2 2026) | -14% improvement |