| Metric | Q3'25 | Q4'25 | Change |
|---|---|---|---|
| Adjusted EPS | $1.81 Q3 (+11% YoY) | $6.31 FY (+7% YoY) | Narrowed to top of guidance range, 7% growth locked |
| 2026 EPS Guidance | Not provided | $6.55-$6.80 | Midpoint implies 6% growth off 2025 |
| 5-Year Capital Plan | $95B-$105B range (Q3) | $103B committed | Locked at high end, +18% vs prior plan |
| Earnings Base Growth | Over 8.5% through 2030 (Q3) | 9.6% through 2030 | +110bps acceleration from capital step-up |
| Data Center ESAs | 3 gigawatts signed (Q3) | 4.5 gigawatts signed | +1.5 gigawatts added, including Microsoft & Compass |
| FFO to Debt | Target 14% by year-end 2025 | 14.8% achieved in 2025 | +80bps beat on target, storm recovery executed |
| 2026 FFO to Debt | 15% long-term target | ~14% forecasted | Step-down due to capital acceleration timing |
| Equity Funding 2027-2030 | 30%-50% of incremental capex | $10B equity needed | ~35% of capex, confirms balance sheet discipline |
| Gas Generation Build | 7.5 gigawatts planned (Q3) | 5 gigawatts under construction | Broke ground, secured supply chain & workforce |
| Battery Storage Deployment | Steady pace mentioned | 4.5 gigawatts through 2031 | First specific battery commitment with ramp timeline |