| Metric | Q3'25 | Q4'25 | Change |
|---|---|---|---|
| Ongoing EPS | $2.79 (Q3 YTD) | $3.80 (Full Year) | 21st consecutive year meeting guidance |
| Data Center Pipeline | 3GW total expectation | 6GW by 2027 | Doubled contracted expectations |
| CapEx Investment | $8B YTD through Q3 | $12B full year 2025 | Largest annual investment in company history |
| Sales Growth | 3% weather-adjusted through Q3 | 2.2% full year actual | 80bps miss vs forecast |
| O&M Expense Growth | 5% forecast | $190M increase actual | In-line with elevated guidance |
| Smokehouse Creek Liability | $410M low-end estimate | $430M low-end estimate | $20M uptick but $360M settled |
| Natural Gas CTs Ordered | 19 turbines on order | 24 gas CTs across vendors | 5 additional GE Vernova units |
| Safe Harbored Renewables | Base capital plan | ~20GW renewable generation storage | Massive tax credit preservation |
| Colorado Rate Case | No filing for 3+ years | Filed electric and gas Q4 | Ends prolonged regulatory lag |
| AFUDC Contribution | $0.19 per share Q3 YTD | $0.27 per share full year | 8¢ quarterly acceleration |