| Metric | Q4'25 | Q1'26 | Change |
|---|---|---|---|
| Ongoing EPS | $0.84 Q1 2025 | $0.91 Q1 2026 | +8.3% YoY growth |
| Electric Revenues Impact | Not disclosed Q4 | +23¢ per share | Massive rate case benefit |
| Interest & Financing Drag | Not specified Q4 | -18¢ per share | Funding cost reality bites |
| Weather Impact | Not disclosed Q4 | -9¢ per share | Warmest winter on record in Colorado |
| Data Center Pipeline | 20+ gigawatt backlog Q4 | Still 20+ gigawatts | No growth in actual pipeline |
| Contracted Data Centers | 2 gigawatts signed Q4 | Still 2 gigawatts | Zero incremental signings despite promises |
| Capital Investment Q1 | $12B full year 2025 | $3B in Q1 | 25% of annual target in one quarter |
| Incremental CapEx Visibility | $10+ billion opportunity | $7+ billion line of sight | 30% visibility on upside |
| Equity Need Satisfied | Not specified Q4 | 50% of 5-year need done | Aggressive pre-funding |
| Marshall Wildfire Liability | $430M low-end Q4 | $460M low-end Q1 | +$30M increase in estimate |