Management credibility scorecard

CleanSpark (CLSK)

9 quarters tracked (Q3'24 to Q3'26) · latest call August 6, 2026
Get the next CLSK call sheet
63%
Kept of 35 resolved
22
Kept or exceeded
13
Missed
14
Still pending
Share count, 3 yrs/yr · structural change

Score History

QuarterCall dateDisclosureFinancial qualityKeptMissed
Q3'26August 6, 20267/121 high, 2 medium flags00Call sheet →
Q2'26May 11, 20263/123 high, 3 medium, 1 low flags13Call sheet →
Q1'26February 5, 20263/123 high, 5 medium, 1 low flags40Call sheet →
Q4'25November 25, 20253/123 high, 4 medium, 2 low flags23Call sheet →
Q3'25August 8, 20253/123 high, 4 medium, 1 low flags32Call sheet →
Q2'25May 8, 20255/123 high, 4 medium, 1 low flags22Call sheet →
Q1'25February 6, 202510/121 high, 5 medium, 1 low flags41Call sheet →
Q4'24December 2, 20249/122 high, 3 medium, 2 low flags31Call sheet →
Q3'24August 10, 20245/123 high, 4 medium, 1 low flags31Call sheet →
Disclosure: the 6-item rubric, each scored 0-2, out of 12. Financial quality: flagged indicators by severity. Kept and missed count the prior-quarter promises scored on that call.

Promise Ledger · All Quarters

MarkedStatusPromise
Q2'26PendingHashrate trending to 55 EH/s by end of year
Currently at 'broken 23' so need to more than double in 7 months, seems impossible
Q2'26MissedContinue share buybacks to reduce dilution
No buybacks mentioned this quarter despite stock likely down significantly
Q2'26DeliveredDisciplined capital deployment
They're barely spending anything ('millions not tens of millions'), probably because they have to be disciplined
Q2'26MissedMove from portfolio formation to commercialization milestones
Still no signed leases, no LOIs announced, just 'progressing' with unnamed tenant
Q2'26PendingSealy 207 MW energizing Q1 2027
Now saying 'just over 200 MW' in 'first half' 2027, already walking it back
Q2'26MissedDAM to generate 4% annualized return on Bitcoin balance
Generated only $4M on ~5200 BTC average balance, well below 4% target when annualized
Q1'26DeliveredGenerate consistent cash from DAM operations
$13M in Q1 up from $9.3M in Q4, showing growth
Q1'26PendingTexas site energization early 2027
Specified Q1 2027 for first 207 MW, on track but not yet proven
Q1'26DeliveredMaintain focus on non-dilutive financing
Used convertible debt and Bitcoin-backed credit lines, though converts are ultimately dilutive
Q1'26DeliveredNo equity issuance via ATM in fiscal 2025
Confirmed no shares issued, completed $600M in buybacks instead
Q1'26DeliveredAchieve 4% annualized yield on DAM strategy
Reported 4.2% annualized return on Bitcoin balance
Q1'26PendingComplete S21XP deployment by calendar 2026
Timeline extended from initial Q1 2026 target to full calendar year
Q1'26PendingSign first AI customer within 12 months
Originally suggested weeks to months, now stretched to 'less than a year'
Q4'25MissedOutpace global hash rate growth
Zero growth while network expanded, losing market share
Q4'25DeliveredSelf-fund operations without equity issuance
No equity issued but used $1.15B convertible debt instead
Q4'25PendingDAM yield target of 4% on entire treasury
Achieving 12% on 40% of stack, but full deployment still in 'crawl phase'
Q4'25MissedContinue pure-play Bitcoin mining focus
Complete reversal to 'digital infrastructure platform' serving AI and HPC
Q4'25MissedAdditional 10 EH deployment on cost-effective timeline
Reduced to 6 EH deployment over extended timeline to calendar 2026
Q4'25DeliveredMaintain 50 EH/s operational hash rate
Held at 50 EH/s but zero growth for first time
Q3'25DeliveredS&P 600 inclusion would enhance institutional ownership
Institutional ownership rose to 64% as promised
Q3'25DeliveredUse revolver for accretive CapEx only
Drew $100M+ on credit line, claims 100% for CapEx
Q3'25MissedMaintain near-100% HODL with strategic monetization
Now willing to sell entire month's production, complete reversal
Q3'25MissedImplement derivative strategies to rapidly advance from crawl phase
Still in crawl phase, pushed timeline to 'within next year' from 'soon'
Q3'25PendingContinue growth towards 57 exahash
Now saying 'additional 10 exahash' but removed timeline, suggests delays
Q3'25DeliveredReach 50 exahash by mid-2025
Hit 50 EH on June 24, actually 6 days ahead of schedule
Q2'25PendingConstruction underway in Tennessee, Wyoming, Georgia
Still talking about 'completion of development' needed
Q2'25DeliveredIndirect expenses to remain relatively flat
Cash overhead decreased 16% quarter over quarter
Q2'25DeliveredComplete ATM offering
Confirmed completed in November, no new shares issued since
Q2'25MissedMaintain industry-leading uptime above 90%
Metric completely disappeared from discussion
Q2'25MissedLaunch Bitcoin treasury management strategy 'shortly'
Still in 'crawl phase' after two quarters of promises
Q2'25PendingReach 50 exahash by mid-2025
Reiterated but now backing away from time-bound targets going forward
Q1'25DeliveredNo reliance on equity for growth funding
Used convertible debt instead, avoided dilution at current prices
Q1'25DeliveredContinue fleet efficiency improvements
Improved from 21.94 to 17.59 J/TH quarter over quarter
Q1'25MissedMaintain industry-leading uptime >97%
Dropped to 94%, blamed on hurricane and fleet moves
Q1'25DeliveredDigital asset management strategy implementation
Team being built, RFPs out, launch expected 'shortly'
Q1'25PendingScale to 50 exahash in 2025
Reiterated H1 2025 target, on track at current 2.2 EH/s monthly run rate
Q1'25ExceededReach 37 exahash by December 2024
Hit 39.1 EH/s, beat target by 5.7%
Q4'24PendingMaintain 50%+ gross margins
No Q4 specific margin disclosure provided
Q4'24DeliveredRemove all miners less efficient than 22 J/TH
Fleet now at 19 J/TH average
Q4'24MissedSandersville 50 MW coming online September
No mention of Sandersville completion; appears delayed
Q4'24PendingDeploy S21 XP miners to Wyoming
7.8 EH/s for delivery 'before year-end', not confirmed deployed
Q4'24DeliveredClose GRIID acquisition this quarter
Closed in October, renamed to Grid infrastructure
Q4'24ExceededAchieve 32 EH/s by end of fiscal year
Hit 33.5 EH/s, beat by 1.5 EH/s
Q3'24DeliveredMaintain operational efficiency leadership
22.3 J/TH fleet efficiency, though taking massive impairment to get there
Q3'24DeliveredContinue HODL strategy
Added 1,579 BTC to holdings
Q3'24PendingWyoming sites operational in H2 2024
Not mentioned this quarter despite Q2 announcement
Q3'24Pending32 EH/s by end of 2024
At 22.3 EH/s currently, needs 10 EH/s in 4 months
Q3'24MissedSandersville 50MW to come online
Still waiting on transformer that failed testing, no timeline now
Q3'24DeliveredAchieve 20 EH/s by end of Q3
Hit 20.1 EH/s, exceeded target
Each row is a promise from the prior call, scored against the quarter in "Marked". Kept-promise rate counts resolved promises only; pending is excluded.
Promise-kept rate counts resolved promises only (pending excluded).
Scores, kept-promise rates, and flags on this site reflect the author's opinion, applying a stated methodology to statements management made on public earnings calls. Informational and educational purposes only - not investment advice, a recommendation, or an offer to buy or sell any security. Sources believed reliable but not guaranteed; the author may hold positions in the securities discussed.

Follow what management promises next