| Metric | Q4'25 | Q1'26 | Change |
|---|---|---|---|
| Core EPS | $0.33 in Q1 2025 | $0.43 in Q1 2026 | +$0.10 or 30% YoY growth |
| Data center final engineering | 2.3 GW at Q4 2025 update | 4.6 GW | +100% quarter-over-quarter surge |
| Rate reductions for vulnerable customers | Down 20% since Jan 2024 (Q4 call) | Down 23% since Jan 2024 | Additional 300 bps improvement |
| Continuous monitoring prevented outages | 12M minutes prevented in all of 2025 | 4M minutes prevented in Q1 2026 alone | Run rate suggests 16M+ for full year |
| System hardening target through 2037 | Not specified in Q4 | Nearly 11,000 miles planned | New long-term visibility provided |
| Undergrounding cost avoidance | Not quantified in Q4 | $100M+ maintenance spend avoided | First quantification of savings |
| Investment grade progress | Fitch IG, others outlook stable | Moody's revised outlook to positive | Momentum building across agencies |
| O&M savings target | 2% to 4% range established Q4 | 2% to 4% range reaffirmed | No change but confidence reinforced |
| Full year 2026 EPS guidance | $1.64 to $1.66 | $1.64 to $1.66 reaffirmed | Unchanged but strong Q1 supports |
| Capital plan size | $73B through 2030 | $73B through 2030 unchanged | Discipline maintained despite opportunities |